Specimen report

Read one before you buy one

An illustrative specimen. The unit, the developer and every figure below are invented to show the structure of a report, this is not a real unit and not a real assessment of anyone.

Report 4

Villa specimen · two-bedroom, 180 m²

Deviation
DeveloperSpecimen Developer (invented)
Contract completion24 Jan 2027
Site visit22 Jul 2026
Attending specialistSpecimen Specialist (invented)
Schedule revisions to date2
Forecast completion12 Mar 202747 days laterAgainst contract: 24 Jan 2027
Built
39.5%

+6.2 pts built

Paid
55.0%
Paid ahead of what is built15.5pts

Work is moving, but slower than the payment schedule assumes. Structure is 71% complete against a milestone that treats it as finished, and the forecast has slipped a further eleven days since the last report. The gap between what has been paid and what has been built is now 15.5 points. The practical consequence is that the next invoice should not be settled in full until the first-floor slab is poured.

Payments against work done

Whether each milestone payment matches what has actually been built.

  • FoundationFoundation complete and cured
    Developer claims
    100%
    Confirmed
    100%
    Amount
    $48,000
    What differs
    Clause 4.1Matches the contract requirement. Nothing outstanding.
  • StructureFrame complete to roof level, first-floor slab poured
    Developer claims
    100%
    Confirmed
    71%29 pts short of the claim
    Amount
    $80,000
    What differs
    Clause 4.2Columns and ground-floor slab are done; the first-floor slab is not poured. Around 70% of the milestone scope is in place.
  • Roof and envelopeRoof structure, waterproofing, external walls closed
    Developer claims
    Confirmed
    8%
    Amount
    $64,000
    What differs
    Clause 4.3Not due. Listed so the next two invoices can be checked against it.

Letter to the developer

Written for you to send. It quotes the clause and asks the question; the decision to send it, and what to accept in reply, is yours.

Under clause 4.2 the Structure stage is treated as complete when the slabs of every floor are in place. At the visit of 22 July 2026, 71% of the positions for that stage were confirmed: the first-floor slab has not been poured.

Please confirm the basis on which US$80,000 is invoiced for this stage, or adjust the amount to the work in place.

Send it as it stands or over your own signature. We are not a party to your contract and do not write to your developer on your behalf.

Schedule forecast

Forecast range12 Mar 202719 Feb 2027 — 30 Apr 2027
Pace5.8 pts / month
Remaining58.5%
ConfidenceMedium
Critical path
  1. 01

    First-floor slab poured and cured

  2. 02

    Roof structure erected

  3. 03

    Envelope closed before the wet season

  4. 04

    Internal finishes

What must happen before the next report
  • First-floor slab poured by 20 September

  • Roof timber on site

  • Crew size back to eight or more

Stated so the next report can be checked against this one rather than replacing it.

Compared with the market

This unit5.8pts7.1 pts / monthTheir median pace
Comparable units on this market6

Six comparable villas on this market are tracked in the same way. This unit is running below their median pace, and the shortfall appeared after the crew was reduced in May rather than being present from the start.

External factors

Listed only where they explain a deviation or put the completion date at risk.

Labour shortage
Effect on schedule31 days

The crew dropped from nine to five in May and has not recovered. This accounts for most of the slippage since the previous report.

Weather and seasonality
Effect on scheduleNot quantified

The wet season starts in November. If the envelope is not closed by then, internal finishes cannot begin and the forecast moves to the upper end of the range.

Technical basis

The evidence behind the figures above. An appendix, not the product.

64 checklist items completed on site
  • Site preparation
    Weight
    5%
    Confirmed
    100%
    Photos
    1
  • Foundation
    Weight
    15%
    Confirmed
    100%
    Photos
    1
  • Structure
    Weight
    25%
    Confirmed
    71%
    Photos
    3
  • Roof and envelope
    Weight
    20%
    Confirmed
    8%
    Photos
    0
  • Services
    Weight
    15%
    Confirmed
    0%
    Photos
    0
  • Finishes
    Weight
    20%
    Confirmed
    0%
    Photos
    0
Observations
  • Rebar spacing in the ground-floor slab matches the drawings at the three points checked.

  • Standing water at the north edge of the plot; drainage not yet installed.

  • Material storage is uncovered, cement bags exposed at the time of the visit.

Photographic record

Grouped by room or zone of the unit, and tied to a stage. The same categories are shot on every visit, so any space can be compared over time.

6 photos
Site and approach · 1 photos
01 · Site and approach

Approach from the access road

Taken22 Jul 2026
StageSite preparation
Facade · 1 photos
02 · Facade

South elevation, columns to first floor

Taken22 Jul 2026
StageStructure
Pool area · 1 photos
03 · Pool area

Pool excavation, no waterproofing yet

Taken22 Jul 2026
StageFoundation
Bedroom 1 · 1 photos
04 · Bedroom 1

Bedroom 1, blockwork complete

Taken22 Jul 2026
StageStructure
Bedroom 2 · 1 photos
05 · Bedroom 2

Bedroom 2, opening for the terrace door not formed

Taken22 Jul 2026
StageStructure
Drainage · 1 photos
06 · Drainage

Standing water at the north edge of the plot

Taken22 Jul 2026

Scope of this check

Basis of the forecast

The forecast is built from the pace recorded over four visits between April and July, applied to the remaining weighted scope, and adjusted for the wet season. It assumes the current crew size holds. A single-figure completion date is not given because four data points do not support that precision.

Checked
  • Physical progress against the stage schedule

  • Milestone requirements against work in place

  • Permits and approvals on the public record, against what is being built

  • Photographic record tied to specific stages

  • Crew size and activity on the day of the visit

Not checked
  • Structural calculations or design adequacy

  • Material certification and testing

  • Whether those permits satisfy the law — that takes a licensed opinion

  • Anything concealed at the time of the visit